San Francisco General Hospital Surgical Suite, a Level One Trauma Center

Chinatown Health Center RenovationProject Information: 
DPW completed this complicated construction project in the Surgical Suite of General Hospital, a Level One Trauma Center, under a tight schedule and completed the project in 18 weeks. The project included the construction and renovation of two operating rooms with new surgical lights and  medical gas column supports. During construction, one operating room had to remain open in order to accomodate the needs of the hospital. Construction access was achieved by building new doors into an adjoining corridor, requiring staff to wear surgical scrubs and attire for initial entry and final exit.The permtting process for this project included approvals from the State of California which added to the complex nature of the project.

Location:
SF General Hospital, 1001 Potrero Ave, Building 5, 6th Floor, Ward 6G

Schedule: 
Construction completed and approved by OSHPD 9/7/10

Cost/Funding:
$157,800

Project Team:
Project Manager: Marilyn Thompson, Bureau of Architecture
Architect: Tom Eliot Fisch
Structural Engineer: Ansari Structural Engineers
Electrical Engineer: FW Associates
Construction Manager: Jorge Gutierrez, Bureau of Architecture

Green Building:
N/A

Contact: Bureau of Architecture DPW (415) 557-4700

Jorge Gutierrez, Jorge.Gutierrez@sfdpw.org

Contractor:
Vila Construction

 

 