Great Highway Pavement Renovation and Streetscape Improvement Project

For more information, regular construction updates, and real-time alerts and announcements by email, sign up here for the Great Highway Renovation Project Newsletter. Archive of past updates below.

 Great Highway at JKF, windmill

 Paving work at Great Highway 5.10.13
 Paving complete at Great Highway to Lincoln
Project Information

The Great Highway will be repaved from Point Lobos to Sloat Boulevard (map). This is a six month project scheduled to finish up in July. Streetscape improvements also will be made to the stretch of road along the Golden Gate Park at Ocean Beach between Fulton and Lincoln. The improvements include new curb ramps, pedestrian crossing and bicycle safety upgrades, and the installation of a landscaped roadway median. Watermain installation work is also being performed as a part of the project.

 
Work includes roadway resurfacing, roadway base repair, concrete sidewalk and curb repairs, adjustment of utility castings to the new roadway surface, ADA curb ramp construction at pedestrian crossing points, and sewer and drainage work.

DPW is managing the construction of the street and streetscape improvements.

Location
Great Highway, from Point Lobos to Sloat Boulevard (map)

Schedule
Construction began in January 2013.

Construction scheduled for completion by the Summer 2013.

Cost/Funding
Total: $7.3 million. The majority of project is funded through the 2011 Road Repaving and Street Safety Bond Program

Contact 
Greg Crump
Public Affairs
(415) 554-6930
greathighway@sfdpw.org

Contractor 
Synergy Project Management
415-815-7992

Newsletter Upates
January 31, 2013:       Work Begins on Great Highway Improvements
February 14, 2013:     Staging Equipment Relocated
March 21, 2013:          Project Slated to be Completed Ahead of Schedule 
April 2, 2013               Great Highway Construction Continues
April 24, 2013             Paving Work Begins Soon
May 1, 2013                Paving Begins Ahead of Schedule
May 14, 2013              A New Road
May 29, 2013              Work now south of Lincoln to Sloat 
June 14, 2013              Paving southern portion begins next week
June 21, 2013              One week to go

 

 